Master Plan Project Construction Update • January 19 – January 26

Construction Update

Progress at UCSF Benioff Children’s Hospital Oakland 

  • The next Master Plan Community Meeting is on Wednesday, April 18 from 6:00 – 7:00 p.m. at the CHORI Library.
  • Ongoing site work includes installation of forms for flatwork, trash compactor foundation, south side storm drain, and pouring of curbs and gutters.
  • On Monday, January 22, the Westside Atrium will open. The double doors exiting out to the new concourse pedestrian path will be closed until concrete is complete.
  • Ongoing construction activities include OPC2 Westside and Service Yard Generator work, painting of stairs 1 and 2, as well as finishes and touch ups to levels 2-6.
  • Installation of wall equipment and rubber sheet on walkways between the existing building and new building on levels 2-5 will occur.
  • The temporary corridor into Orthopedics and Lab Blood Draw is closed. If the Orthopedics registration/waiting area or Lab Blood Draw is your intended destination, staff will greet and escort you through the clinical space to be registered.
  • New temporary walls will be installed in the existing OPC to allow for removal of the temporary pedestrian tunnel into Orthopedics.
  • Testing and commissioning the mechanical, electrical and plumbing systems of the new building will occur.

Upcoming Weekend Work

  • Possible weekend work to install interior finishes and complete site and Service Yard work may occur on:
    • January 20
    • January 27
    • February 3
    • February 10
    • February 17