Master Plan Project Construction Update • July 21 – July 28

Construction Update

Progress at UCSF Benioff Children’s Hospital Oakland

  • The next Master Plan Project Community Meeting is scheduled for October 18 from 6 to 7 p.m. at the CHORI Library.
  • Ongoing construction activities, including exterior enclosure of building on South Side, casework installation, painting, and MEP trim finishes and installation.

Upcoming Weekend Work

  • July 22 – Install Concrete Approach & Window Curtain Wall South Side
  • July 29 – Install Window Curtain Wall South Side & Interior Finishes
  • August 5 – Install Window Curtain Wall South Side & Interior Finishes
  • August 12 – Install Window Curtain Wall South Side & Interior Finishes
  • August 19 – Install Exterior Framing & Stucco and Site Work
  • August 26 – Install Exterior Framing & Stucco and Site Work