Master Plan Project Construction Update • May 6 – May 13

Construction Update

Progress at UCSF Benioff Children’s Hospital Oakland

  • There will be work within the existing Outpatient Center (OPC1) west atrium this week. This may result in some minor noise within the building.
  • There will be minor material deliveries to the new Outpatient Center (OPC2) site this week. Delivery trucks will enter the site at 52nd Street and unload within the fenced boundaries.
  • PG&E will continue to run new power lines beneath 52nd Street today, May 6, throughout the week.
  • Signs for the Residential Parking Permit (RPP) program have been installed on the streets that have submitted petitions to the City of Oakland and enforcement has begun.

SAFETY NOTE: Please only use the crosswalks at MLK Jr. Way that are open and operational. Do not cross MLK Jr. Way from the construction side of 52nd Street. The crosswalk and sidewalk along the construction site are closed.