Master Plan Project Construction Update • November 3 – November 10

Construction Update Progress at UCSF Benioff Children’s Hospital Oakland 

  • Starting 11/6, the temporary corridor into Orthopedics and Lab Blood Draw will be closed. If the Orthopedics registration/waiting area or Lab Blood Draw is your intended destination, staff will greet and escort you through the clinical space to be registered.
  • New temporary walls will be installed in the existing OPC to allow for removal of the temporary pedestrian tunnel into Orthopedics.
  • Complete remaining construction work on first floor of OPC.
  • Ongoing construction activities include work on OPC2 Westside, Service Yard Generator, and MEP finish trims.
  • Starting and testing the mechanical, electrical and plumbing systems of the new building.
  • In addition, activities include installation of casework and trenching by CUP loading dock for utilities.

Upcoming Weekend Work

  • November 11 – Install Interior Finishes, Site work & Generator (tentative)
  • November 18 – Install Interior Finishes, Site work & Generator (tentative)