by primary | Apr 23, 2016 | Construction Updates, E-Blast, Uncategorized
Master Plan Project Construction Update • April 22 – 29 Construction Update Progress at UCSF Benioff Children’s Hospital Oakland Tomorrow, Saturday, April 23, the entire westbound lane on 52nd Street will be blocked off to allow a flatbed truck to remove...
by primary | Apr 23, 2016 | Construction Updates, E-Blast, Uncategorized
Master Plan Project Construction Update • April 15 – 22 Construction Update Progress at UCSF Benioff Children’s Hospital Oakland Structural steel, metal decking and rebar for the new Outpatient Center (OPC2) will continue. Delivery trucks for this work...
by primary | Apr 8, 2016 | Construction Updates, E-Blast, Uncategorized
Master Plan Project Construction Update • April 8 – April 15 Construction Update Progress at UCSF Benioff Children’s Hospital Oakland The last concrete foundations for the new Outpatient Center (OPC2) were placed last week. The first load of structural...