Master Plan Project Construction Update • February 23 – March 2 Construction Update The West Entry of OPC, Concourse and Westside of the atrium is now open. Ongoing construction activities include landscaping, sitework, and punch work...
by primary | Feb 16, 2018 | Construction Updates, E-Blast, Uncategorized
Master Plan Project Construction Update • February 16 – February 23 Construction Update The West Entry of OPC, Concourse and Westside of the atrium is now open. Ongoing construction activities include landscaping, sitework, and punch work for interior...
by primary | Feb 3, 2018 | Construction Updates, E-Blast, Uncategorized
Master Plan Project Construction Update • February 2 – February 9 Construction Update Progress at UCSF Benioff Children’s Hospital Oakland The Westside of the atrium is now open. Ongoing construction activities include OPC2...