Master Plan Project Construction Update • January 8 – 15

Construction Update

Progress at UCSF Benioff Children’s Hospital Oakland

  • The new garage entry and exit off MLK Jr. Way is open and many temporary signs are in place. These signs will soon be replaced with permanent ones after an assessment of their effectiveness.
  • Additional striping will be done on the first level of the parking garage.
  • Construction of the interior infection control walls in the OPC1 West atrium has begun. This will continue for 1-2 weeks until the atrium area is completely sealed from the occupied floors and café area.
  • Additional lighting will be installed in the corridors on each floor of OPC1 since the natural light from the West atrium has been closed off. These will be installed over the next 1-2 weeks.

SAFETY NOTE: Please only use the crosswalks at MLK Jr. Way that are open and operational. Do not cross MLK Jr. Way from the OPC2 side of 52nd Street. The crosswalk and sidewalk along the OPC2 site are closed