Master Plan Project Construction Update • November 11 – 18

Construction Update

Progress at UCSF Benioff Children’s Hospital Oakland

  • Concrete anchors will be drilled on the 6th floor this week. This will cause some noise.
  • Ongoing construction activities including temporary roofing installation, elevator installation, framing and wall layout will continue this week.