Master Plan Project Construction Update • October 13 – October 20

Construction Update

Progress at UCSF Benioff Children’s Hospital Oakland

  • Next community meeting will be held on October 18.
  • Ongoing construction activities include OPC2 Westside site and Service Yard Fuel Tank work, rubber flooring and casework installation, MEP Finish Trims, painting and ceiling grid work, temp power removal, ceiling light activation on all floors and trenching by CUP loading dock for utilities.